12th span of Padma bridge installed

0
125

News desk: The twelfth span of Bangladesh’s biggest infrastructure project Padma Bridge has been installed, making 1,800 metres of the bridge visible.

The span was installed atop pillars 11 and 12 on Monday noon.

According to project details, on October 14, 2018, Prime Minister Sheikh Hasina unveiled the name plaque of Padma Bridge Toll Plaza at the Mawa end.

The national economy is expected to witness 1.2 percent GDP growth rate, while 0.84 percent poverty will be reduced every year after completion of the bridge to be built with an estimated cost of Taka 30,193.39 crore.

The first span of the Padma Bridge was installed on September 30, 2017. The second span was installed four months later on January 28, 2018 while the third one was placed on March 11, after one and a half months.

According to the engineers concerned, a total of 41 spans will be installed on 42 concrete pillars to complete the bridge.