The minister made the statement while attending the question and answer session of the National Parliament on Thursday, reported UNB.
He said: “The installation of the remaining spans and columns will hopefully be done by December 2018.
“However, the finalisation of the design of its piles is getting delayed slightly at 14 locations due to the difference in the river’s soil layers.”
The minister said the process continues to solve the problems fast in consultation with local and foreign experts.
He said the overall physical progress in the Padma Bridge project is 50%.
One span (superstructure) of the bridge has already been installed, while another will be installed this month, he added.